- Project Number:
- SP 069-070-027
- Contract Number:
- Other Project Numbers:
- CP 0000-259423 SP 069-070-027
- Project Description:
- SP 069-070-027, CP 0000-259423 - 6" Paint Edgeline Striping
- Construction Location:
- City or Township:
- Bid Opening:
- 04/05/2018 10:00 AM
- Expected Award Date:
- 04/24/2018
- Project Start Date:
- 06/04/2018
- Construction Start Date:
- 06/04/2018
- Construction End Date:
- 07/27/2018
- Work Type:
- Traffic Control
- Project Type:
- Road and Street
- Highest Funding Level:
- Federal
- DBE Project:
- No
CP 0000-259423, SP 069-070-027, MN Proj # HSIP 6918 (204)
6" Paint Edgeline Striping
Project Major Items:
Number | Item | Units | Quantity |
---|
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2582.502 | 6" SOLID LINE PAINT | LIN FT | 594,277.00 |