- Project Number:
- SAP 069-703-016
- Contract Number:
- 365478
- Other Project Numbers:
- CP 0103-352324 (Tied) SAP 069-703-016
- Project Description:
- CP 0103-352324 (Tied), SAP 069-703-016 CSAH 102 to TH 169 - Culvert Replacement
- Construction Location:
- City or Township:
- Bid Opening:
- 03/29/2018 10:00 AM
- Expected Award Date:
- 04/10/2018
- Project Start Date:
- 08/06/2018
- Construction Start Date:
- 08/06/2018
- Construction End Date:
- 09/21/2018
- Work Type:
- Pipe and Culvert
- Project Type:
- Road and Street
- Highest Funding Level:
- State
- DBE Project:
- No
CP 0025-365478 (Low), SAP 069-625-017; CP 0066-363849 (Tied);
CP 0103-352324 (Tied), SAP 069-703-016
Culvert Replacement, Plant Mixed Bituminous Patches, Storm Sewer Replacement, Grading and Aggregate Base.
Project Major Items:
Number | Item | Units | Quantity |
---|
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2104.501 | REMOVE PIPE CULVERTS | LIN FT | 316.00 |
2104.513 | SAWING BIT PAVEMENT (FULL DEPTH) | LIN FT | 288.00 |
2105.604 | GEOTEXTILE FABRIC TYPE VI | SQ YD | 1,692.00 |
2130.501 | WATER | M GALLON | 6.00 |
2211.503 | AGGREGATE BASE (CV) CLASS 5 | CU YD | 444.00 |
2360.501 | TYPE SP 12.5 WEARING COURSE MIX (2;C) | TON | 207.00 |
2451.501 | STRUCTURE EXCAVATION CLASS E | CU YD | 1,818.00 |
2451.503 | GRANULAR BACKFILL (CV) | CU YD | 1,158.00 |
2451.507 | GRANULAR BEDDING (CV) | CU YD | 140.00 |
2501.511 | 24" RC PIPE CULVERT | LIN FT | 256.00 |
2501.515 | 24" RC PIPE APRON | EACH | 12.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | WORK ZONE SPEED LIMIT | LUMP SUM | 1.00 |
2573.502 | SILT FENCE; TYPE HI | LIN FT | 600.00 |
2573.550 | EROSION CONTROL SUPERVISOR | LUMP SUM | 1.00 |
2573.560 | CULVERT END CONTROLS | EACH | 6.00 |
2575.572 | RAPID STABILIZATION METHOD 4 | SQ YD | 1,200.00 |
2582.502 | 4" BROKEN LINE PAINT | LIN FT | 60.00 |
2582.502 | 4" DBLE SOLID LINE PAINT | LIN FT | 432.00 |