Number | Item | Units | Quantity |
---|
2021.501 | MOBILIZATION | LUMP SUM | 1.00 |
2021.601 | MOBILIZATION, SEAL COAT | LUMP SUM | 1.00 |
2021.601 | RAILROAD PROTECTIVE SERVICES | LUMP SUM | 1.00 |
2104.501 | REMOVE PIPE CULVERTS | LIN FT | 265.00 |
2104.505 | REMOVE BITUMINOUS PAVEMENT | SQ YD | 1,288.00 |
2104.513 | SAWING BIT PAVEMENT (FULL DEPTH) | LIN FT | 426.00 |
2105.602 | TEMPORARY STREAM DIVERSION SYSTEM | EACH | 1.00 |
2105.604 | GEOGRID | SQ YD | 375.00 |
2105.604 | GEOTEXTILE FABRIC TYPE VI | SQ YD | 837.00 |
2106.607 | GRANULAR EMBANKMENT (CV) | CU YD | 96.00 |
2118.501 | AGGREGATE SURFACING CLASS 5 | TON | 714.00 |
2123.503 | MOTOR GRADER | HOUR | 16.00 |
2123.507 | 0.5 CU YD SHOVEL | HOUR | 10.00 |
2123.525 | 8 TON STEEL-WHEELED ROLLER | HOUR | 16.00 |
2130.501 | WATER | M GALLON | 30.00 |
2131.502 | CALCIUM CHLORIDE SOLUTION | GALLON | 1,905.00 |
2211.501 | AGGREGATE BASE CLASS 5 | TON | 500.00 |
2211.503 | AGGREGATE BASE (CV) CLASS 5 | CU YD | 303.00 |
2215.501 | FULL DEPTH RECLAMATION | SQ YD | 16,950.00 |
2215.604 | BASE STABILIZATION (BASE ONE) | SQ YD | 15,216.00 |
2355.502 | BITUMINOUS MATERIAL FOR FOG SEAL | GALLON | 1,698.00 |
2356.505 | BITUMINOUS MATERIAL FOR SEAL COAT | GALLON | 4,441.00 |
2356.506 | BITUMINOUS SEAL COAT | SQ YD | 13,458.00 |
2357.502 | BITUMINOUS MATERIAL FOR TACK COAT | GALLON | 943.00 |
2357.606 | BITUMINOUS MATERIAL FOR SHOULDER TACK | GALLON | 669.00 |
2360.501 | TYPE SP 9.5 WEARING COURSE MIX (3;C) | TON | 3,238.00 |
2360.505 | TYPE SP 9.5 BIT MIXTURE FOR ENTRANCES (3,C) | TON | 10.00 |
2451.501 | STRUCTURE EXCAVATION CLASS E | CU YD | 1,760.00 |
2451.503 | GRANULAR BACKFILL (CV) | CU YD | 523.00 |
2451.507 | GRANULAR BEDDING (CV) | CU YD | 193.00 |
2501.515 | 18" RC PIPE APRON | EACH | 4.00 |
2501.515 | 60" RC PIPE APRON | EACH | 2.00 |
2501.521 | 22" SPAN RC PIPE-ARCH CULV CL IIA | LIN FT | 32.00 |
2501.521 | 28" SPAN RC PIPE-ARCH CULV CL IIA | LIN FT | 40.00 |
2501.525 | 22" SPAN RC PIPE-ARCH APRON | EACH | 2.00 |
2501.525 | 28" SPAN RC PIPE-ARCH APRON | EACH | 2.00 |
2501.561 | 18" RC PIPE CULVERT DES 3006 | LIN FT | 78.00 |
2501.561 | 60" RC PIPE CULVERT DES 3006 CL II | LIN FT | 82.00 |
2511.501 | RANDOM RIPRAP CLASS III | CU YD | 8.00 |
2540.602 | MAIL BOX SUPPORT | EACH | 8.00 |
2563.601 | TRAFFIC CONTROL | LUMP SUM | 1.00 |
2563.601 | TRAFFIC CONTROL, SEAL COAT | LUMP SUM | 1.00 |
2563.601 | WORK ZONE SPEED LIMIT | LUMP SUM | 1.00 |
2573.533 | SEDIMENT CONTROL LOG TYPE STRAW | LIN FT | 782.00 |
2575.572 | RAPID STABILIZATION METHOD 4 | SQ YD | 1,059.00 |
2580.603 | INTERIM PAVEMENT MARKING | LIN FT | 19,040.00 |
2580.603 | INTERIM PAVEMENT MARKING | LIN FT | 19,040.00 |
2582.501 | PAVT MSSG PREF TAPE GR IN | SQ FT | 124.00 |
2582.502 | 24" SOLID LINE EPOXY | LIN FT | 42.00 |
2582.502 | 24" SOLID LINE PAINT | LIN FT | 42.00 |
2582.502 | 4" BROKEN LINE EPOXY | LIN FT | 210.00 |
2582.502 | 4" BROKEN LINE PAINT | LIN FT | 210.00 |
2582.502 | 4" DBLE SOLID LINE EPOXY | LIN FT | 4,175.00 |
2582.502 | 4" DBLE SOLID LINE PAINT | LIN FT | 4,175.00 |
2582.502 | 4" SOLID LINE EPOXY | LIN FT | 960.00 |
2582.502 | 4" SOLID LINE PAINT | LIN FT | 960.00 |
2582.502 | 6" SOLID LINE EPOXY | LIN FT | 10,100.00 |
2582.502 | 6" SOLID LINE PAINT | LIN FT | 10,100.00 |
2582.602 | PROTECT PAVEMENT MESSAGE | EACH | 2.00 |