- Project Number:
- 21011
- Contract Number:
- 21011
- Other Project Numbers:
- Project Description:
- 2021-2022 Dust Control
- Construction Location:
- City or Township:
- Bid Opening:
- 03/16/2021 10:00 AM
- Expected Award Date:
- 03/23/2021
- Project Start Date:
- 05/24/2021
- Construction Start Date:
- 05/24/2021
- Construction End Date:
- 06/25/2022
- Work Type:
- Aggregate
- Project Type:
- Road and Street
- Highest Funding Level:
- Local
- DBE Project:
- No
2021-2022 Dust Control on Crow Wing County gravel roads.
Project Major Items:
Number | Item | Units | Quantity |
---|
2131.506/00010 | CALCIUM CHLORIDE SOLUTION | GALLON | 274,152.00 |
2131.606/00020 | MAGNESIUM CHLORIDE SOLUTION | GALLON | 274,152.00 |